![]() System that automates the submission, review, approval, construction, and archival of utility installation requests at TxDOT. User purges an installation request or a. Form ROW-U-35. STANDARD UTILITY AGREEMENT. U-Number: U-xxxxx. District: Houston. Utility Joint Use Acknowledgment - ROW-U-JUA and/or Utility Installation Request - Form 1082. (Attachment “E”). All attachments. Section 6: Utility Considerations in Right of Way Project Closeout Introduction Before any right of way project closeout can occur, determine that all costs are in and there are no outstanding parcel, utility adjustment, or relocation assistance issues and/or payments. The following are utility considerations in a project closure. District Responsibilities Review files to verify that: • all utility final billings are paid; • reimbursements to LPAs are complete, if applicable; and • all required Utility Joint Use Acknowledgements, Release of Easements, Subordination of Mineral Leases, and recorded Quitclaims are submitted to the ROW Division. Periodically, Districts should review their master list for projects eligible for closure. The longer an older project stays open, the more difficult it is to finalize; therefore, Districts should promptly request closure. Division Responsibilities • Print out a utility list of all “U” numbers for the project acquired by computerized application. • Retrieve files from the utility list. • Retrieve any additional files discovered in a physical search of the ROW Division Utility Portfolio Section files. • Examine all files for final payment and discard duplicates. • Review all Utility Joint Use Acknowledgements, recorded quitclaims, release of easements, and subordination of mineral leases. Red alert 3 uprising free download full game for windows 7. Retain all keep items for permanent records. • Reduce approved plans or “as-built” plans to half scale. • Make annotations on the title sheet of the right of way map listing “U” numbers applicable to the project. • Deliver files to Contracts and Finance Section with the completed Utility Branch closeout notice. • During ROW Division review of the District’s project closeout request, if any items in the file are missing or incorrect, the Division will: • notify the District of its findings and request action to resolve any items noted; • notify its Contracts and Finance Section that project closeout will be delayed due to the items noted; and • check with the District on a quarterly basis until outstanding items are resolved.
0 Comments
Leave a Reply. |
AuthorWrite something about yourself. No need to be fancy, just an overview. ArchivesCategories |